Daewoo Engineering & Construction (E&C) has since February 9th completed setting up a heat exchange facility at the Nigeria NLNG Train 7 project site in Nigeria.

According to information available to THE MATRIX, this cryogenic heat exchanger is pivotal in liquefying substantial quantities of natural gas and facilitating refining processes, a key component in the LNG production chain.

Read Also: Black Market: Naira appreciates by 7.62% to N2100 against Pounds

The installation features Air Products’ AP-C3MR technology, making the new Main Cryogenic Heat Exchanger (MCHE) the world’s largest of its kind to utilize this technology, as announced by the company on Monday.

Advertisement

Valued at 2.1 trillion won ($1.58 billion), the Nigeria NLNG Train 7 project involves building LNG liquefaction and support facilities.

Lee Won-gil, project manager at Daewoo E&C said of the project, “The successful installation of the cryogenic heat exchanger, transported from the United States to Nigeria across the Atlantic Ocean, underscores the recognition of our extensive expertise and experience accumulated over the years”