David Umahi Reveals FG’s 2025 Road Plan

Published

on

The Federal Government will prioritize completing four major road projects per geographical zone in 2025, according to Minister of Works David Umahi. This means that existing projects will be completed before new ones are started.

Umahi disclosed that this decision was made in reaction to economic difficulties like inflation, the naira’s floating value, and the elimination of fuel subsidies, all of which have considerably increased the cost of infrastructure.

He went on to say that the Tinubu-led administration took over 2,600 road projects worth N13 trillion, emphasizing the necessity to reallocate resources and concentrate on finishing four major projects in each zone to guarantee the timely delivery of vital infrastructure.

“This administration inherited 2,600 projects with a total cost of N13 trillion. With the floating of the naira and the fuel subsidy removal, inflation has had a significant impact.

Advertisement

Read Also: Stop Building New Structures On Coastal Highway In Hope For  Compensation- Umahi

“What we are doing is to select a number of projects in 2025 that are ongoing. We do not intend to start new projects. So, four projects are going to be selected per zone and then put money that will see these projects completed,” Umahi said.

The Works Minister’s announcement means that in 2025, 24 road projects, four from each of Nigeria’s six geopolitical zones, will be selected for completion, ensuring a more focused use of resources.

The Minister of Works further elaborated that the Highway Development and Management Initiative (HDMI) has been crucial in mobilizing the private sector to take part in Nigeria’s road infrastructure development.

He emphasized that, under this initiative, 63 roads have already been engaged, with private companies financing and constructing the roads, which will then be tolled for cost recovery.

Advertisement

Read Also: Lagos Calabar Highway: Umahi Closes Landmark Beach, Begins Demolition Of Shanties Along Right Of Way

Umahi noted that the Keffi-Makurdi Road is fully completed but has not yet been opened for tolling, as the government is working closely with the Federal Ministry of Finance to implement a paperless, cashless tolling system. This modern approach to toll collection is aimed at ensuring seamless transactions and minimizing disruptions for road users.

In addition to this, the Minister confirmed that several other key road projects, including the Lagos-Ibadan Expressway, Makurdi to Ninth Mile Road, and the Abuja to Kano Road, will also be tolled upon completion, ensuring these roads are properly maintained and sustained through the revenue generated from tolling.

Moreover, he highlighted that beyond the HDMI initiative, the Lagos-Calabar Coastal Highway, which is expected to see its first section completed by May 2025, along with sections 2A and 2B of the Second Niger Bridge, will also be tolled once construction is completed, ensuring continued maintenance and financial sustainability.